Need a bigger electrical panel? Start with PG&E first
Even a same-size panel swap needs a PG&E application. When PG&E gets involved, how long each kind of job takes, and why we start it as soon as plans are ready.
PG&E lists even a same-size replacement, such as an old 100-amp panel for a new 100-amp one, among the jobs that need an application through its Your Projects portal, because only PG&E or workers it authorizes may disconnect and reconnect its service.
The state set two targets for PG&E's own steps: an average of 30 business days for a main panel upgrade with no PG&E work in front of the meter, and an average of 182 calendar days for a new or upgraded service line.
PG&E's latest report put the average for finished jobs that needed only a new or upgraded service line (Rule 16) at 307 calendar days from application to power, counting the owner's and agencies' time as well as PG&E's own; jobs that also needed PG&E line work averaged 439.
News · October 14, 2026 · PG&E said it began notifying customers in October whose projects could be delayed, including work to connect new customers or upgrade their service, with more detail expected in mid-December. [1]
Say you're finally going electric: a heat pump, an induction range, maybe a charger in the garage. Or you're building a backyard cottage. Then the electrician looks at your old 100-amp panel and shakes their head. The drawings and the city permit are steps you can push along. PG&E's part runs on its own clock.
On every ADU we build around the Bay Area, PG&E is the part we watch most. Here's when PG&E gets involved, the steps from application to power, how long each kind of job takes, and how some homes avoid a bigger service altogether.
Does a panel upgrade need PG&E?
Yes, even when the amps stay the same. PG&E lists "Replacement with no change to service (ex. old 100-amp panel to a new 100-amp panel)" among the jobs that need an application, because the service has to be disconnected and reconnected [2]. Only people PG&E authorizes may connect or disconnect its service conductors [3][4].
PG&E draws the line like this. A "like-for-like" job replaces equipment "with same ampacity rating and in same location". An upgrade replaces it "with an increase in ampacity rating (e.g., 100A to 200A)" and must meet all of PG&E's current requirements. A same-amp panel that doesn't match the old one's "shape, layout, dimensions, and number of sockets" counts as an upgrade too [3]. When you add load, PG&E checks whether the lines and transformer that serve your home can carry it. If they can, there's no PG&E upgrade, just the disconnect and reconnect [5].
What it means for you. Replacing your main panel is a PG&E job, even at the same size. Swapping a breaker inside it isn't a panel replacement [3]. The question is which kind of PG&E job, because that decides the clock you're on.
How long does PG&E take?
The state set two different targets for PG&E's own steps, and PG&E reports how it's doing on each [6][7].
Job
State target, PG&E's steps only
PG&E's latest average, its own steps
PG&E's latest average, end to end
Main panel upgrade, with no PG&E work in front of the meter
30 business days on average, 45 at most
26 business days
39 business days
New or upgraded service line only (Rule 16)
182 calendar days on average; 335 at most for 95% of requests
113 calendar days
307 calendar days
The targets count only the steps PG&E controls, and the clock starts once PG&E deems the application complete [6]. For service-line jobs, PG&E's end-to-end figure runs from application to power and also counts the owner's and agencies' time [7]. PG&E's averages cover only jobs already energized by June 30, 2026, and they cover all customer types, not only homes. Jobs that also needed PG&E line work (Rules 15 and 16 together) averaged 439 days end to end [7]. It says its main panel upgrades "typically only involve a disconnection and reconnection of service once the main panel is installed" [7].
What it means for you. If PG&E has to bring a bigger service to your house, plan in months, not weeks. If it only has to unplug and replug, it's a much shorter wait.
What are the steps, from application to power?
Apply. You or your contractor submit the request through PG&E's Your Projects portal, or by phone with its Building and Renovation Service Center [3][5]. PG&E's guide says to list all your electrical load needs, including the panel size and the new loads. Upload a site plan, photos of the existing service and the proposed panel location. Submit "as soon as you have your project details and/or building permit." And give the legal and billing contact separately from the contractor's, to avoid billing and correspondence delays [5].
Intake. A PG&E Job Owner contacts you within three to five business days, depending on the PG&E document [3][8]. PG&E's Greenbook says to send the documents and pay any engineering advance within 35 calendar days, or the application can be cancelled. PG&E then completes intake within 66 calendar days of submission [3]. Its web FAQ instead gives 30 calendar days from the day you receive the advance invoice [8], so ask your Job Owner which deadline applies. PG&E's panel-upgrade guide says a single-family home may owe an initial advance of up to $5,000 for PG&E's assessment, refunded or credited toward any balance owed [5].
Design and contract. If PG&E has work to do on its side, PG&E or an approved applicant designer designs it. PG&E then sends a contract, which must be signed within 90 days [3][5][9].
Your side of the work. On an underground service, you dig the trench and lay the conduit, PG&E inspects them, and you install the meter panel [9][4].
The city inspection. PG&E connects only after the city tells it the work is installed, inspected and safe to energize [4]. It energizes only within six months of that approval. After that, you need a new one [3].
Power. On a panel upgrade with a new underground service line, PG&E's chart lists "approx. 6-8 weeks" for scheduling its crew for final installation after the city's meter release [9]. When PG&E only has to reconnect, its guide says it reconnects and energizes the home "typically within one day" after the panel is replaced and the city inspector approves [5].
Some residential jobs up to 320 amps, such as a panel change or upgrade, can use PG&E's faster Express Connect track. Its map shows up to 34 calendar days from application to approval, then an average of 66 calendar days to power [8][10]. If the load check shows the existing lines can't carry the new load, the job moves to the regular process [10].
Who does, and pays for, what?
With overhead service, PG&E brings the service drop to the attachment point on your house, and you own the weatherhead, mast and meter panel [3]. With underground service, you provide the trench and conduit on your property, and PG&E installs and owns the service conductors [4]. On an upgrade, PG&E's Greenbook says new conductors may be needed at your cost, along with trenching and substructure [3].
A few rules shape the bill:
Moving the panel. If a remodel moves the panel and PG&E's existing service conductor won't reach the new spot, "complete service replacement is required, and the applicant is responsible for all costs" [3]. Moving PG&E's service for an addition or remodel at your request is at your "total estimated costs" [4].
Paying first. Payments are due before PG&E starts its work [4].
The allowance. PG&E's residential allowance for line and service extensions is $3,255 per meter or dwelling unit [11]. Whether it applies to your upgrade is a question for your Job Owner.
Help in 2026. PG&E's income-qualified EV charging rebate offers up to $5,000 for a panel upgrade plus an eligible charger. Apply before a contractor from its Trade Ally Network buys and installs the equipment [12]. Silicon Valley Clean Energy, whose service area includes Los Altos, Mountain View, Cupertino and Saratoga, offers a $1,000 panel add-on when you also install a core rebate appliance. It covers panel work up to 100 amps; going bigger, up to 200 amps, takes an exception, which may not be granted for a home undergoing a remodel [13]. The state's HEEHRA single-family rebates cover heat pump heating and cooling, not panels, and they've been fully reserved since February 24, 2026 [14]. The federal home-improvement credit, which could cover a 200-amp-plus panel needed for qualifying equipment, ended with 2025 [15].
Can you avoid a service upgrade?
Sometimes. PG&E's own guide says "you may be able to electrify your home's appliances without a panel upgrade." It names smart panels, smart breakers, 120-volt heat pump water heaters and circuit-sharing devices, which "could pause your EV charger when another energy-intensive device is running" [16]. Its sample is a 2,400-square-foot home on a 100-amp panel. With standard appliances, its new electric loads come to 122 amps. Share one circuit between the EV charger and the dryer, pick lower-wattage appliances, and the same home fits at 89 amps [16]. For solar, batteries or an EV charger, PG&E says a meter socket adapter from its approved list can avoid a panel upgrade. Only single-meter homes at 240 volts and 200 amps or less, with a form 2S meter socket that meets PG&E's clearance standards, qualify [17].
Since February 25, 2026, PG&E's tariff also doesn't count "controlled load" as connected load. That's equipment behind a UL 3141-certified power control system that keeps the home's draw at or below the connected load of its other equipment [18]. How PG&E applies that to an ordinary home's request is worth asking your Job Owner.
What it means for you. Ask your electrician to run the load numbers both ways, with and without load management, before anyone orders a 200-amp panel.
What's changing in 2026 and 2027?
PG&E says it will defer about $2 billion of planned 2027 work, and that "new customer connections" may take longer [19]. In October it began telling customers whose projects could be delayed, including service upgrades, with more detail expected in mid-December [1].
Help is coming for small jobs. As our 2027 dates guide notes, a 2026 state law, SB 1196, has the Public Utilities Commission set timelines by September 30, 2027 for "small energization projects." Those are jobs that need no distribution or service line extension or upgrade, including ones whose only upgrade is a new meter that PG&E or the city requires [20]. When it sets them, the Commission must require PG&E to accept the application at the same time you apply for the building permit [20]. A service upgrade that needs new or bigger PG&E lines isn't "small" under that definition.
On the city side, San Mateo can issue an electrical service upgrade as an express permit, with no plan check and no drawings, when the work needs no plan review [21]. In Palo Alto, power comes from City of Palo Alto Utilities, not PG&E, so its own rules apply [22]. Our Palo Alto guide covers them.
What Amiari knows
Our take: on a remodel or ADU, the PG&E request is the one item you can't rush later, so start it early.
What we see on our jobs. On every ADU we build around the Bay Area, PG&E is the part we watch most. When a job needs a meter upgrade or its own panel, PG&E's part can easily take four to six months, sometimes more, and following up doesn't speed it up. So once the plans are ready, we have the homeowner sign in to their PG&E account and start the request, because that wait can hold up the whole job.
PG&E says the same. Its own guide says to submit the request "as soon as you have your project details and/or building permit" [5].
Leave the meter panel where it is, if you can. If PG&E's existing service conductor won't reach the new spot, moving it turns a panel job into a full service replacement at your cost [3].
Ask about load management first. A bigger service isn't the only answer, and PG&E's own guide shows how some homes skip it [16].
Keep your own contact details on the application. PG&E's tip is to give the legal and billing contact separately from the contractor's, to avoid billing and correspondence delays [5].
PG&E's clock doesn't start until your application is complete, so apply first.
Amiari Construction builds custom homes, ADUs and additions, and remodels kitchens and baths, on the Peninsula.
How we checked this: In November 2026, Amiari Construction read PG&E's Electric Rules 2, 15 and 16, its 2026 Greenbook, its panel-upgrade, Express Connect and disconnect-reconnect guides, its September 2026 energization report to the state and its 2026 news posts, the Public Utilities Commission's energization decision, SB 1196 in the Legislature's own data download, PG&E's, Silicon Valley Clean Energy's, the state's and the IRS's program pages, and San Mateo's permit pages. For Palo Alto we relied on the utility rules we read in October.
Step by step
01Find out which kind of job it isAsk your electrician whether the new loads fit your existing service, or whether PG&E must bring a bigger service to the house.
02Apply as soon as you have the detailsSubmit the PG&E request through Your Projects, or have your contractor do it, with the load details, site plan and photos PG&E's guide says to include.
03Keep the owner's side movingPay any engineering advance and sign any contract on time, and, on an underground service, have the trench, conduit and meter panel ready for PG&E's and the city's inspections.
04Ask about avoiding the upgradeAsk whether load-management devices or lower-wattage appliances let the house add electric loads without a bigger service.
Need a bigger electrical panel? Start with PG&E firstamiari.com · 8 min read
Planning a remodel, ADU or electric upgrade?Send us your address and what you want to add. We'll tell you which kind of PG&E job it's likely to be and what to have ready before you apply.
Have plans already, or need help getting started? We’ll help coordinate the right team and guide your project from the first ideas through construction. Prefer email? info@amiari.com
Share your projectAnswer a few quick questions about your project and goals.
We connectWe'll reach out within one business day to learn more and discuss your needs.
Plan and estimateWe'll provide preliminary insights and a clear path forward with next steps.
A
AmiariWe reply within one business day
San Carlos Whole Home Reconfiguration
Hi, we're Amiari. You were reading “Need a bigger electrical panel? Start with PG&E first”. Let's talk about your home.