State law lets a backyard ADU sit 4 feet from the side and rear lines. A protected tree, the sewer's slope, the power and the fire map often decide the spot.

Amiari Construction · Published Oct 17, 2026 · Last reviewed Oct 16, 2026 · 7 min readinShare
A freshly dug shallow trench crossing a sunny backyard lawn just behind a large shade tree
A trench across a backyard lawn · Photo: Famartin, CC BY-SA 4.0 (cropped)
In short
  • California lets a new backyard ADU sit 4 feet from the side and rear lot lines, but a protected tree's root zone, the sewer's slope to the street, the power service and a mapped fire zone often decide where it actually fits.
  • At the plumbing code's quarter inch per foot, a 120-foot sewer run needs 30 inches of fall, and fixtures below the top of the main sewer drain to a sump and a pump.
  • A new ADU in a Very High fire zone is built to the state's wildfire code, which until mid-2027 keeps gable-end and dormer vents 10 feet from lot lines; an emergency rule that took effect in January 2026 reached local High zones too, so ask the building department what applies on your permit date. Among our 12 cities, only Palo Alto, Cupertino and Saratoga have Very High land.

What's under the yard decides where the cottage goes

Example lot from above: house up front, a cottage in the back corner 4 feet from the lines, a neighbor's oak past the fenceIllustrative drawing
01 / 06

State law lets a new detached ADU sit 4 feet from the side and rear lot lines, so owners picture it in the back corner [2].

Illustrative drawing of an example San Mateo lot: the oak's rings, the sewer's fall, the power trench and a fire-zone vent rule

News · September 30, 2026 · In PG&E's September 30, 2026 report, finished jobs that needed only a new service line averaged 307 days from application to power, including 113 days on PG&E's own steps. [1]

The rule everyone hears is 4 feet. California lets a new backyard ADU sit as close as 4 feet to the side and rear lot lines, and a city must approve one of up to 800 square feet that meets the state's limits [2]. From January 2027, that's two of them [3]. So owners picture the cottage tucked into the back corner, where it takes the least yard.

Take an example lot in San Mateo, 50 by 150 feet, with the house up front. Just over the back fence stands the neighbor's oak, 10 inches across. Four things decide whether that corner works, and it pays to check them before anyone draws.

Can a protected tree, even the neighbor's, limit where an ADU goes?

It can. In San Mateo, an oak is a protected heritage tree from 10 inches across, measured 54 inches above the ground [4]. Cutting its roots within six times the trunk's diameter needs a permit. Construction within ten times needs a tree protection plan by a certified arborist before the building permit is issued [4]. For a 10-inch oak, those rings are 5 feet and 8 feet 4 inches from the trunk. The city's guidelines say the plan covers trees on neighboring property too [5].

On the example lot, the oak stands 2 feet past the fence. A cottage at the 4-foot line puts its back wall 6 feet from the trunk: outside the root-cutting ring, inside the protection zone. That means an arborist's plan, and digging footings inside the zone only if the city arborist approves [4].

Does a city's tree rule even apply to the ADU the state makes it approve? State ADU law never mentions trees. For the ADUs a city must approve, it bars local standards the statute doesn't list [2]; for other ADUs, a city's ADU ordinance may set objective "landscape" standards [6]. In 2023, HCD told Santa Clarita to remove a rule applying its oak ordinance to ADUs [7]. Palo Alto changed its code in 2024 so a protected tree may be removed to make room for an ADU under its state-standard rules [8]. San Carlos's code still applies its tree rules to second units [9], and San Mateo's code doesn't say. Los Altos's checklists for its pre-approved and permit-ready ADU plans ask for an arborist report when work reaches the inner two-thirds of a protected tree's dripline [10][11]. We know of no court ruling on it, so ask your city in writing. And the neighbor's tree is the neighbor's, even where its roots reach into your yard [12].

The cost to the household: an arborist's report before design, and a cottage that may move a few feet toward the middle of the yard.

How much must an ADU's sewer slope, and when does it need a pump?

The plumbing code wants a building sewer to slope at least a quarter inch per foot toward the sewer it drains to [13]. From the back corner of a 150-foot lot, the run can be 120 feet, which takes 30 inches of fall. Only with the code official's approval, and where the street sewer's depth or the building's structure or layout makes that slope impractical, may a 4- to 6-inch line slope an eighth of an inch per foot [13].

A yard that slopes down toward the back eats that margin fast. Fixtures below the top of the main sewer must drain to a sump and be pumped up [13]. Fixtures on a floor lower than the next upstream manhole cover need a backwater valve [13], and some districts, such as West Bay, which serves most of Menlo Park and parts of Atherton, set that line a foot higher [14][15][16]. For new buildings, Cupertino Sanitary District requires a pump when the lowest floor with fixtures sits less than a foot above that manhole's rim [17].

Then there's the tie-in. State law lets a city or district require a separate sewer connection for a new detached ADU, with a fee proportional to its size or its plumbing fixtures, and the 750-square-foot fee exemption doesn't cover connection charges [18]. Whether the cottage may share the house's line is up to the local sewer agency, the city or a sanitary district. In Hillsborough, building a new structure that needs a sewer connection on a lot that already has a private lateral (the pipe from the house to the public sewer) puts that lateral up for evaluation, and repair or replacement if needed [19]. In San Carlos, work that adds toilets needs the lateral to pass inspection before occupancy, unless a current certificate is on file [20].

If the slope isn't there, the cottage gets a pump and valves, and that's cheapest to learn before the floor height is set.

Who brings power to a new ADU, and how long does it take?

PG&E delivers power in 11 of the 12 cities, and Palo Alto runs its own utility [21][22]. When PG&E builds a new service, the owner is responsible for a clear route, the trenching and the conduit on the property [23]. PG&E's allowance is $3,255 per meter or dwelling unit, and since July 2024 there is none for new buildings that also use gas or propane, apart from some projects that were in design review by then and are energized by June 30, 2027 [24]. Sewer and water lines can't share PG&E's trench [25].

The bigger cost is time. PG&E's own posting puts its average invoice for an ADU's new electric service at $4,831.86, with 303 days from application to power, for jobs finished by August 2025 [26]. The state's targets count only PG&E's steps: 182 days on average for a service line, and no more than 335 for 95 percent of jobs [27][28]. The newest report, in the box above, shows 307 days start to finish [1].

In Palo Alto, the utility normally allows one service per lot. A cottage gets its own meter by swapping the house's meter panel for a two-meter panel, and it needs its own address [22][29]. The city's standard fee for a single-phase underground service up to 200 amps is $4,093 when no transformer upgrade is needed, before your trench [30].

So ask the utility as soon as the spot is set.

Fire hazard zone maps changed in 2025, and so did the building rules

The State Fire Marshal released new local fire hazard maps for San Mateo and Santa Clara counties on February 24, 2025, with Moderate, High and Very High zones [31][32], and the city or its fire district had 120 days from receiving them to adopt them [33]. Among our 12 cities, Very High land is only in Palo Alto, Cupertino and Saratoga. Hillsborough, San Carlos, Redwood City and Los Altos have High and Moderate. San Mateo and Belmont have Moderate only, and Menlo Park, Atherton and Mountain View have none [32].

From January 1, 2026, an emergency rule extended the state's wildfire building code from Very High zones to local High zones as well [34]. The Commission readopted that rule for 90 days in May 2026, and we found no record of a second readoption [35][36]; the permanent version it took up in August 2026 takes effect July 1, 2027 [37][38]. So ask the building department which rules apply on your permit date. Saratoga applies the code in Moderate zones too, and so does San Mateo Consolidated Fire, which serves San Mateo and Belmont [39][40][41]. A new ADU in a covered zone needs, among other things, a Class A roof, ember-resistant vents (listed or tested types, or fine noncombustible mesh on roof vents), and windows with a tempered pane or another approved glazing. Under the 2025 code, its gable-end and dormer vents must sit at least 10 feet from lot lines [42], which rules them out on the wall facing a line 4 feet away; the permanent revision, from July 2027, applies the 10-foot rule to roof ridge and off-ridge vents instead [37].

A fire zone alone doesn't bar an ADU. HCD says a High zone "is not a conclusive rationale" for restricting ADUs, and a city's area limits can't preclude the ADUs it must approve [43]. In Very High zones, state law also requires 100 feet of defensible space, up to the property line [44]. The Board of Forestry's 5-foot "Zone 0" rule, approved August 19, 2026 [45], was withdrawn from state review on September 8 and isn't in force [46].

What to check first, in order, before you place an ADU

  1. The fire map. It's a lookup, and it sets how the cottage is built.

  2. The trees. A tape measure and the city's rule show how close you can dig.

  3. The sewer. The elevations of the cottage floor and the sewer set the floor height, or a pump.

  4. The power. Ask the utility as soon as the spot is set; its answer comes last.

  5. The city, in writing. Ask which of these rules it applies to your ADU.

Amiari Construction builds ADUs and additions on the Peninsula.

How we checked this: In October 2026, Amiari Construction read the state laws in the legislature's own data, HCD's handbook and letters, the 2025 plumbing code, the wildfire code's rulemaking texts, PG&E's and Palo Alto's utility rules and reports, the State Fire Marshal's 2025 maps, and tree, sewer and fire records for the 12 cities and their districts.

Step by step

01Look up the fire mapFind the lot on the 2025 map and ask the building department which wildfire rules it applies.
02Measure the treesMeasure trunks near the spot, yours and the neighbors', and look up the city's protection zone.
03Find the sewer's fallCompare the cottage's floor with the sewer at the street and its nearest upstream manhole.
04Ask about power earlyAsk PG&E, or Palo Alto's utility, how the cottage would be served, and how long that takes.
05Ask the city in writingAsk the city, and the sewer district if there is one, whether their tree, sewer and fire rules apply to your ADU, before anyone draws.
Sources
  1. PG&E, Biannual Energization Report pursuant to Decision 24-09-020 (public version), filed September 30, 2026Read Oct 16, 2026
  2. Government Code §66323, ADUs a city must approve ministerially, as amended by SB 543, effective January 1, 2026 (read in the legislature's own data download)Read Oct 16, 2026
  3. AB 956 (Quirk-Silva), Chapter 791, Statutes of 2026: chaptered text (read in the legislature's own data download)Read Oct 16, 2026
  4. City of San Mateo Municipal Code, chapter 13.40, Protected Trees (current through October 8, 2026)Read Oct 16, 2026
  5. City of San Mateo, Protected Trees Administrative Guidelines (revised July 2025)Read Oct 16, 2026
  6. Government Code §§66314 and 66315, local ADU standards (read in the legislature's own data download)Read Oct 16, 2026
  7. HCD, ADU ordinance review letter to Santa Clarita (March 24, 2023)Read Oct 16, 2026
  8. City of Palo Alto, City Council action minutes, April 1, 2024 (item 10, tree ordinance amendments)Read Oct 16, 2026
  9. San Carlos Municipal Code §18.18.020, landscaping standards: applicabilityRead Oct 16, 2026
  10. City of Los Altos, City Permit-Ready ADU Submittal Requirements (checklist, item 5; PDF created December 3, 2025, no printed date)Read Oct 16, 2026
  11. City of Los Altos, Pre-Approved ADU Submittal Requirements (checklist; PDF created December 3, 2025, no printed date)Read Oct 16, 2026
  12. Civil Code §§833 and 3346, trees and roots on a neighbor's land (read in the legislature's own data download)Read Oct 16, 2026
  13. 2025 California Plumbing Code (Title 24, Part 5), §§708.1, 709.1, 710 and 718.1, the official read-only edition linked by the Building Standards CommissionRead Oct 16, 2026
  14. West Bay Sanitary District, Code of General Regulations (revised July 22, 2026), §§401 and 406Read Oct 16, 2026
  15. West Bay Sanitary District, What We Do (service area)Read Oct 16, 2026
  16. City of Menlo Park, Sanitary sewer (Public Works: water, stormwater and solid waste)Read Oct 16, 2026
  17. Cupertino Sanitary District, frequently asked questions (private sewage pumps, backflow devices, lateral video inspection)Read Oct 16, 2026
  18. Government Code §66311.5 (formerly §66324), ADU utility connections and fees (read in the legislature's own data download)Read Oct 16, 2026
  19. Hillsborough Municipal Code, chapter 13.32, sewer connections (§§13.32.090, 13.32.120)Read Oct 16, 2026
  20. San Carlos Municipal Code, chapter 13.05, sewer lateral inspection and replacementRead Oct 16, 2026
  21. California Energy Commission, Electric Load Serving Entities (IOU & POU) map layerRead Oct 16, 2026
  22. City of Palo Alto Utilities, Rule and Regulation 20, special electric utility regulationsRead Oct 16, 2026
  23. PG&E Electric Rule 16, service extensionsRead Oct 16, 2026
  24. PG&E Electric Rule 15, distribution line extensions (allowances)Read Oct 16, 2026
  25. PG&E, Electric and Gas Service Requirements (Greenbook), 2026, §§3.6 and 3.9Read Oct 16, 2026
  26. PG&E, Average Project Cost and Timeline: New Residential Electric and Gas Service (SB 1210 posting, November 2025)Read Oct 16, 2026
  27. CPUC, energization timelines fact sheet, Decision 24-09-020 (September 2024)Read Oct 16, 2026
  28. CPUC Decision 24-09-020, energization timelines (Ordering Paragraph 1)Read Oct 16, 2026
  29. City of Palo Alto Utilities, single-family residential project application packet, 2026Read Oct 16, 2026
  30. City of Palo Alto, FY 2027 Adopted Municipal Fee Schedule (adopted June 15, 2026), electric service connection feesRead Oct 16, 2026
  31. Office of the State Fire Marshal, Fire Hazard Severity Zones (local responsibility area maps released February 24, 2025, Phase 2)Read Oct 16, 2026
  32. OSFM, recommended fire hazard severity zones, February 2025, Phase 2: acres in local responsibility areas by cityRead Oct 16, 2026
  33. Government Code §51179, local designation of fire hazard severity zones (read in the legislature's own data download)Read Oct 16, 2026
  34. State Fire Marshal emergency rule SFM EF 01/25, California Wildland-Urban Interface Code §101.3.1, as filed with the Secretary of State (approved by the Building Standards Commission October 15, 2025)Read Oct 16, 2026
  35. California Building Standards Commission, Emergency Rulemaking page (SFM EF 01/25 and its readoption request)Read Oct 16, 2026
  36. California Building Standards Commission, meeting minutes, May 6, 2026 (agenda item 5, SFM EF 01-25 readoption; vote on p. 4)Read Oct 16, 2026
  37. State Fire Marshal SFM 04/25, California Wildland-Urban Interface Code, final express terms for the Building Standards Commission's August 25, 2026 meetingRead Oct 16, 2026
  38. California Building Standards Commission, CALCode Quarterly, Fall 2026 (August 2026 approvals take effect July 1, 2027)Read Oct 16, 2026
  39. Saratoga City Code, article 16-52, wildland-urban interface (Ordinance 414, November 5, 2025)Read Oct 16, 2026
  40. San Mateo Consolidated Fire Department, Board packet, November 19, 2025 (Ordinance 2025-003, §302.3.1)Read Oct 16, 2026
  41. San Mateo Consolidated Fire Department, Board minutes, November 19, 2025 (Ordinance 2025-003 adopted)Read Oct 16, 2026
  42. 2025 California Wildland-Urban Interface Code (Title 24, Part 7), chapter 5, final express terms (SFM 08/24)Read Oct 16, 2026
  43. HCD, Accessory Dwelling Unit Handbook, March 2026Read Oct 16, 2026
  44. Government Code §51182, defensible space in very high fire hazard severity zones, as amended by AB 1455 (read in the legislature's own data download)Read Oct 16, 2026
  45. Board of Forestry and Fire Protection, Notice of Proposed Emergency Action, Zone 0 Defensible Space (August 20, 2026)Read Oct 16, 2026
  46. Office of Administrative Law, recent actions on emergency regulations (Board of Forestry, Zone 0, file 2026-0828-03E, withdrawn September 8, 2026)Read Oct 16, 2026

Last reviewed Oct 16, 2026

Share it on LinkedIn

The post picks up the cover, the title and the link.

inShare on LinkedIn
Where would it fit on your lot?Send us your address. We'll look at the yard, the hose path, the sewer and the power, and tell you what to ask the city before anyone draws.
Get a lot check
© 2026 Amiari Construction · CSLB #1138009(650) 667-9493 · info@amiari.com