In Palo Alto, under a temporary rule in effect through December 31, 2026, a new two-story home, new second story or second-story expansion over 150 square feet goes through Individual Review, with neighbor notice, only if it doesn't meet the city's objective two-story standards.
Most trees are protected at 15 inches across, six native species, the coast live oak among them, at 11.5 inches and coast redwoods at 18, all measured 4½ feet up; most development applications need an arborist's statement on them.
City of Palo Alto Utilities runs the electric, gas, water and wastewater service; its June 2026 rules allow one electric service point per lot, more only when one isn't feasible, and let CPAU require separate services for an ADU sold separately from the house.
What does my Palo Alto project need?
Kitchen or bath remodel
Who reviews it
Building
Rules to check
Instant permit: licensed contractors only, same footprint, no added fixtures or equipment, no wall, window, door or structure changes and no panel upgrade[6]
Kitchen circuits or outlets added or changed under a permit: a 50-amp, 240-volt-capable circuit, or a pathway with reserved panel space, for a future electric range[7]
A circuit added or altered within 3 ft of a gas dryer: a 30-amp version; wall framing removed or replaced within 3 ft of a gas water heater: room for a heat pump one[7]
No tree statement if the work changes no footprint and involves no grading, trenching, paving or landscaping change that could alter water to established plants[2]
The state's list doesn't show the city's energy ordinance; city staff list electric readiness when installing gas equipment as already in effect for new construction and major remodels; confirm at plan check[8][9]
The detached ADU state law protects: up to 800 sq ft, 4 ft from the side and rear lines, 16 ft tall, or 18 within half a mile's walk of a major transit stop or high-quality transit corridor[23]
Larger ADUs: up to 900 sq ft, or 1,000 with two or more bedrooms (an attached one no more than half the house's size); up to 800 sq ft in all exempt from floor area, lot coverage and house size limits[23]
Meet the objective two-story standards, or apply for Individual Review to deviate (temporary rule through Dec 31, 2026)[1][13]
Covers a new second story or an expansion over 150 sq ft, counting all second-story additions after Nov 19, 2001[1]
On a standard R-1 lot: 30 ft to the roof peak, or 33 with a roof pitched 12:12 or steeper[1]
Side daylight plane 10 ft up at the interior side lot line, 45°; rear 16 ft up at the rear setback line, 60°[1]
Substandard and flag lots: 17 ft and one habitable floor[1]
IR: neighbors get mail within 3 days and have 21 days to comment, then 14 days after notice of the Director's proposed decision to ask for a free hearing; a council appeal carries a fee[19][11]
Single-Story Overlay: 17 ft and one habitable floor[1]
Arborist's statement in most cases; tree zone radius 10× the trunk's diameter[2]
Homes first permitted before 2011 adding or altering more than 1,000 sq ft score points from an efficiency menu[7]
A protected tree comes out only on the urban forester's findings, such as no financially feasible design alternative[2]
CPAU since July 1, 2026, when you pay nothing toward a transformer upgrade: $4,093 for a 200-amp-or-less underground service, $4,530 at 400 amps; more capacity or system upgrades: CPAU's estimate[30]
The charges adjust each July with a construction cost index; check the current figure with CPAU[31][30]
All-electric enforcement for new buildings suspended in February 2024[32][33]
AB 130 pauses new building standards for homes, Oct 1, 2025 through June 1, 2031, with narrow exceptions[34][35]
Work costing at least half the house's market value is a "substantial improvement": the lowest floor goes at least 1 ft above the base flood elevation in most zones[16]
On a standard R-1 lot, the height limit rises by half the lift, up to 33 ft (20 ft under a Single-Story Overlay) (Second-story addition, New custom home)[1]
An ADU gets no flood height bonus (ADU or junior ADU)[23]
Build and inspect: Certify the floor elevation (new construction or a substantial improvement)[16]
The house is a significant historic building (Category 1 or 2, or in a historic district)
Historic Resources Board (Second-story addition, New custom home)
Category 1 or 2, or any building in a historic district, counts as significant[17]
Exterior changes to a significant single-family house: the board reviews, advice "voluntary, not mandatory"[17]
ADUs and junior ADUs on inventory properties skip that review (ADU or junior ADU, Garage conversion)[17]
Demolishing a significant building outside downtown: 60-day wait, board recommendation, council may extend to a year (New custom home, Garage conversion)[17][26]
In 2026, a 1923 garage in Professorville went to the board on its demolition application. (Garage conversion, New custom home)[26]
Pick a project to see which Palo Alto reviews, local rules and steps apply, each with its source. Each line's number matches the sources below the article.
Palo Alto has its own oaks, its own utility and its own way of reviewing a second story, so a project here crosses more city desks than you might expect. The short answer: Planning and Development Services reviews the design, the building official's team checks plans and inspects, the urban forester speaks for protected trees, and City of Palo Alto Utilities sizes your power, gas, water and sewer [1][2][3]. On some lots, flood and historic rules join in.
It's a busy town for small homes. From 2015 through September 2025, the city received 920 ADU and junior ADU applications and issued 725 permits, 101 of them in 2025's first nine months [4]. By our count of state permit records, Palo Alto permitted 391 ADU units from 2023 through 2025, the most of the 12 Peninsula cities we track [5].
Who reviews a Palo Alto remodel, ADU or new home?
A kitchen remodel may never see a planner. A second story will.
Project
Review path
Trees
Also check
Kitchen or bath remodel
Building permit; an instant permit for licensed contractors doing same-footprint work that adds no fixtures or equipment, with no wall, window, door or structure changes and no panel upgrade (fees by city) [6]
No tree statement if the work changes no footprint and involves no grading, trenching, paving or landscaping change that could alter water to established plants [2]
Kitchen circuits or outlets added or changed under a permit: the city's ordinance asks for 240-volt readiness; confirm at plan check [7][8][9]
ADU, junior ADU or garage conversion
Ministerial review under state law [10][11]
A state-protected ADU needs only your own tree statement [2]
One electric service point per lot, unless one isn't feasible and CPAU allows more [12]
Second-story addition
Objective two-story standards, or Individual Review to deviate (temporary rule through 2026) [1][13]
Arborist's statement in most cases [2]
Daylight planes, Single-Story Overlay, flood zone [1]
New custom home
Second-story rules if it has two. No knocking the old house down: it's deconstructed after a salvage survey [1][14][15]
Arborist's statement; removal only on the urban forester's findings [2]
Flood, historic and utility service [16][17][18]
Amiari Construction builds custom homes, ADUs and additions and remodels kitchens and baths on the Peninsula.
Does a second story still need Individual Review?
Only if it doesn't meet the city's objective two-story standards, under temporary rules now set to run through December 31, 2026. The zoning code says single-family development "shall comply with the objective standards for two-story development," and an applicant "seeking to deviate" applies for Individual Review (IR) [1]. That covers a new two-story home, a new second story, or a second-story expansion of more than 150 square feet, counting all second-story additions after November 19, 2001 [1]. The council adopted these rules as temporary ordinances in December 2024 and January 2025 and has extended them through 2026; it takes up a permanent version on November 2, 2026 [13].
On a standard R-1 lot, the base limits are 30 feet to the roof peak (33 with a roof pitched 12:12 or steeper), a side daylight plane starting 10 feet up at the interior side lot line at 45 degrees, and a rear one starting 16 feet up at the rear setback line at 60 [1]. Substandard and flag lots are held to 17 feet and one habitable floor [1].
IR faces the neighbors. Adjacent owners and residents get mail within three days and have 21 days to comment, then 14 days after notice of the Director's proposed decision to ask for a free hearing; a council appeal carries a fee [19][11]. In a June 2026 case, a neighbor showed the drawings had their house more than four feet too tall. The architect re-measured with a laser, and the revised plans brought the new home down seven inches [11]. Palo Alto neighbors measure in inches.
Some Eichler tracts went further, with a Single-Story Overlay: 17 feet and one habitable floor, created with signatures from 70 percent of the properties, or 60 percent where every property has recorded deed restrictions limiting it to one story [1][20][21]. The city's 2018 Eichler guidelines were adopted as voluntary [20][21].
Amiari builds additions and custom homes and can walk the lot with you before anyone draws.
Which trees are protected in Palo Alto?
Measure the trunk 4½ feet off the ground. A coast live oak, valley oak, blue oak, California black oak, bigleaf maple or incense cedar is protected at 11.5 inches across, a coast redwood at 18, and most other trees at 15 [2][22]. Each gets a tree protection zone with a radius ten times the trunk's diameter: about 17 feet for a 20-inch oak [2]. Removing more than 15 percent of a protected oak's functioning root area in 36 months counts as excessive pruning [2]. Here the oak gets a vote.
Most development or demolition applications need a city-listed arborist's statement on the protected trees [2]. On a single-family lot, a protected tree comes out for a project only on the urban forester's findings, such as no "financially feasible design alternative": one that adds no more than twice the tree's reproduction cost or 10 percent of the project valuation, whichever is greater [2]. ADUs get some room: a tree may come out to fit the small ADU state law protects, or where a larger ADU can't otherwise meet the state's minimums; either way, the city's tree manual sets the replacement trees [2][23]. The council rewrote these rules in 2022 [22][2]; our guide to where an ADU can go covers trees, sewer and power.
Amiari can walk your lot with you and see where the big trees stand.
What changes if your lot is in a flood zone?
In FEMA's Special Flood Hazard Area, the 50 percent line is the one to know. If your remodel or addition costs at least half the house's market value before the work, Palo Alto calls it a "substantial improvement." Then, as with new construction, the lowest floor goes at least one foot above the base flood elevation in most zones, and an engineer or surveyor certifies it at the end [16]. New basements are out, and existing ones can't grow [16].
The zoning code gives some height back: on a standard R-1 lot, the house's limit rises by half the lift needed to reach base flood elevation, up to 33 feet (20 under a Single-Story Overlay), and the daylight planes rise with it [1]. An ADU doesn't get that bonus [23]. Creekside neighborhoods know why. Land along San Francisquito Creek was mapped as a flood zone in 1997, and the creek flooded in February 1998 [24][25].
Amiari builds additions and custom homes and can look at your lot with you.
Does historic review apply to your house?
Buildings on the city's historic inventory rated Category 1 or 2, and every building in a historic district, count as "significant" [17]. For a significant single-family house, the Historic Resources Board reviews exterior changes, but its advice is "voluntary, not mandatory," and ADUs and junior ADUs on inventory properties skip that review [17]. Demolishing a significant building outside downtown is different: the building official waits 60 days, the board makes a recommendation, and the council can stretch the wait to a year [17][26].
Professorville, subdivided in 1889 for Stanford professors and known for brown shingles and gambrel roofs, shows how far that reaches [27]. In 2026 an owner there applied to take down a 1923 detached garage, alongside an application for a junior ADU, a detached ADU and an attached garage. Because it sits in the locally designated historic district, the garage went to the Historic Resources Board in June for its recommendation [26]. In Palo Alto, even a garage can be historic.
Amiari builds ADUs and additions and can walk the lot with you.
What do Palo Alto's ADU rules in PAMC 18.09 allow?
The city's code lists one attached ADU, one detached ADU and one junior ADU per single-family lot, and staff say state law now adds a conversion ADU [23][28]. The detached ADU state law protects is up to 800 square feet, 4 feet from the side and rear lines and 16 feet tall, or 18 within half a mile's walk of a major transit stop or high-quality transit corridor [23]. Larger ADUs follow local standards: up to 900 square feet, or 1,000 with two or more bedrooms (an attached one no more than half the house's size), with up to 800 square feet in all exempt from floor area, lot coverage and house size limits [23]. No parking is required, even for a converted garage. Rentals run 30 days or more, and no separate sale except as state law allows [23]. For 2027 unit counts, see how many ADUs you can build.
News · August 17, 2026 · The Palo Alto City Council voted 4-3 to advance ADU changes that include a 1,200-square-foot maximum, and sent separate sale of ADUs back to its planning commission. [28]
That isn't law yet. On September 9 the council pulled the second reading from its consent calendar and sent it back to staff to return "ASAP"; it wasn't on a council agenda through November 2 [29]. The code copy we read on October 27 still says 900 and 1,000 [23]. Ask before you size the unit.
State law gives the city 15 business days to say whether an application is complete, and 60 days from a complete application to approve or deny it when a house or multifamily building already stands on the lot [10]. The city's own average from application to ready-to-issue was 178 days in the first nine months of 2025, counting weekends and applicants' resubmittal time [4].
Amiari builds ADUs and can look at your lot with you.
What does the city-run utility mean for your ADU or remodel?
Your power company is City Hall. City of Palo Alto Utilities (CPAU) runs electric, natural gas, water, wastewater and fiber service, so a bigger service for an ADU or an electric remodel is a CPAU job [3]. Since July 1, 2026, the city's fee schedule charges $4,093 to connect a single-family underground service of 200 amps or less, "with or without an ADU," and $4,530 at 400 amps [30]. Those prices apply when you don't have to pay toward a transformer upgrade or replacement; connections needing more capacity or system upgrades pay CPAU's estimate of the installation cost [18][30]. From January 1 to June 30, 2026, the same services cost $3,940 and $4,360 under CPAU's own rate schedule [18]. The charges adjust each July with a construction cost index, so check the current figure with CPAU [31][30].
CPAU's electric rule, in effect since June 1, 2026, says "Only one Point-of-Service is allowed per lot"; when one isn't feasible, CPAU may allow more at its sole discretion [12]. If an ADU is sold or conveyed separately from the house, CPAU may require, at the owner's expense, its own electric service, water service and sewer lateral [12]. A junior ADU isn't a separate unit for water, sewer or power at all [23]. Digging near the gas meter? The rules set a 10-foot buffer around gas service lines; work there without CPAU's permission can bring a disconnection and fees [3].
Amiari builds ADUs and additions and can walk the lot with you, meter to back fence.
Is Palo Alto still all-electric, and what does AB 130 freeze?
Not for new homes, for now. In February 2024 the council suspended enforcement of its rule that new buildings be all-electric, after a federal appeals court ruled against Berkeley's gas ban [32][33]. AB 130 then paused new state and local building standards for homes from October 1, 2025 through June 1, 2031, with narrow exceptions [34][35]. Palo Alto moved first: the council adopted Ordinance 5665 on September 8, 2025, 7-0, as an emergency ordinance, to have its energy code amendments in place "before the AB 130 moratorium begins" [36][7].
Under 5665, a permitted kitchen job that adds or alters circuits or outlets gets a 50-amp, 240-volt-capable circuit, or a pathway with reserved panel space, for a future electric range. A circuit added or altered within 3 feet of a gas dryer gets a 30-amp version, and removing or replacing wall framing within 3 feet of a gas water heater means leaving room for a heat pump one [7]. Homes first permitted before 2011 that add or alter more than 1,000 square feet score points from an efficiency menu; ADUs meet only the state's mandatory measures [7]. Our kitchen permit guide explains the wiring.
The Energy Commission approved 5665 in January 2026 [37]; the Building Standards Commission's 2025 list, read October 27, shows other Palo Alto ordinances but not 5665 [8]. City staff list electric readiness when installing gas equipment as "already in effect" for new construction and major remodels, and an air-conditioner-to-heat-pump rule from January 1, 2027 [9]. Ask plan check what applies to yours.
Amiari remodels kitchens and baths and builds custom homes on the Peninsula.
How we checked this: In October 2026, Amiari Construction read Palo Alto's zoning, tree, flood, historic and deconstruction codes, council, board and hearing records from 2024 to 2026, CPAU's 2026 rules and charges, the city's energy ordinance and its state filings, AB 130, HCD's ADU handbook, the city's ADU reports, the state's permit records and local news.
Step by step
01Look up the lotFind the zoning, any Single-Story Overlay, the FEMA flood zone and whether the house is on the historic inventory.
02Count the treesMeasure trunks 4½ feet up and get the arborist's statement where it's required.
03Pick the review pathADU review, the objective two-story standards or Individual Review, and the Historic Resources Board for a significant building.
04Call the utility earlyAsk City of Palo Alto Utilities about service size and the electric service point.
05Apply for the building permitInclude the energy rules, flood elevations and, for a tear-down, the salvage survey.
06Build and inspectMeet the tree-protection conditions, certify the daylight plane if asked and the floor elevation for new construction or a substantial improvement in a flood zone.
Palo Alto remodel, ADU or new home: the city rules, in orderamiari.com · 9 min read
Planning a project in Palo Alto?Send us your address. We'll look at the lot, the trees, the second-story limits and the utility service, and tell you what to ask the city before anyone draws.
Have plans already, or need help getting started? We’ll help coordinate the right team and guide your project from the first ideas through construction. Prefer email? info@amiari.com
Share your projectAnswer a few quick questions about your project and goals.
We connectWe'll reach out within one business day to learn more and discuss your needs.
Plan and estimateWe'll provide preliminary insights and a clear path forward with next steps.
A
AmiariWe reply within one business day
San Carlos Whole Home Reconfiguration
Hi, we're Amiari. You were reading “Palo Alto remodel, ADU or new home: the city rules, in order”. Let's talk about your home.