From January 1, 2027, California cities must approve two new detached ADUs on a single-family lot instead of one, and for up to two ADUs on a lot, impact fees count only the living space above 750 square feet.
Neither law says whether an application filed in 2026 and decided in 2027 gets the new rules, so ask your city in writing before you pick a filing date.
Use November and December to check the yard, the sewer, the trees, the power and your loan; PG&E's posted average for a new ADU electric service with no line extension was 303 days from application to power.
Countdown to January 1, 2027
January 1, 2027: AB 956 and SB 1117 take effect. [1][2]
Before Jan 1
Pace the hose pathEvery first-floor outside wall must sit within 150 feet of the fire access road, measured around the building, unless the fire department allows more (for example, with sprinklers). [16]
Find what's under the yardSewage usually needs at least a quarter inch of fall per foot, and a cottage that sits too low needs a pump. [18]
Check for protected treesSan Mateo protects any oak, and Menlo Park any native oak, from 10 inches across. [19][20]
Start with PG&E earlyPG&E's posted average for a new ADU electric service with no line extension was 303 days from application to power. [21]
Call your lenderFannie Mae allows up to three ADUs on a one-unit home only with a UAD 3.6 appraisal, and counts rent from only one ADU. [5]
Ask the city in writingNeither law says which date decides the rules and fees for an application filed in 2026 and decided in 2027. [1][2]
Free webinar, November 19"Building Your ADU", online, 5:30 to 6:30 pm. Free; registration is required. [8] Event page
On Jan 1
Two detached ADUsCities must approve two new detached ADUs on a single-family lot, and can't require side and rear setbacks of more than 4 feet. [1]
800 sq ft cap still allowedOn the state path, a city may cap each new detached ADU at 800 square feet of livable space. [1]
Smaller impact feesFor up to two ADUs on a lot, impact fees count only the living space above 750 sq ft. [2]
No city vote neededRegular statutes start on January 1 after a 90-day period from enactment. [3]
The permit clock15 business days to call your application complete, then, on a lot with an existing house, 60 days to approve or deny it, or it's deemed approved. [9]
Build order mattersOnce two detached ADUs have been built on the state path, the city doesn't have to approve a junior ADU, though it may. [1]
A third ADUWith more than two ADUs, impact fees on a unit with more than 750 sq ft of living space can count the whole unit. [2]
Its own water or sewer lineAs today, a new detached ADU can be required to have its own connection, which may carry a fee sized by its square feet or drainage fixture units. [2]
April 2027: HUD rentsHUD says it will post revised Fair Market Rents from its rechecks. [10]
Countdown to January 1, 2027, Pacific time, with the checklist for before, on and after the day
January 1, 2027, a Friday and a state holiday, is when two California laws change the rules for building out back [1][2][3][4]. A city must then approve two new detached ADUs on a single-family lot instead of one, and for up to two ADUs, impact fees on a bigger unit count only the space above 750 square feet [1][2]. Your yard and PG&E's calendar won't change overnight, so the useful work starts now.
When does each ADU change land, from now to 2027?
The interactive figure on this page runs this countdown live.
When
What happens
Source
Now to December 31, 2026
The state path guarantees one new detached ADU on a single-family lot. Impact fees on an ADU over 750 square feet are scaled to the house's size and can count the whole unit.
[1][2]
November 2, 2026
Fannie Mae and Freddie Mac make the UAD 3.6 appraisal format mandatory for new appraisal reports, with exceptions, for lenders that asked before November 2, through May 19, 2027.
[5][6][7]
November 19, 2026, 5:30 to 6:30 pm
The San Mateo County ADU Resource Center's free online webinar, "Building Your ADU".
[8]
January 1, 2027 (Friday, a state holiday)
AB 956 and SB 1117 take effect.
[1][2][3][4]
January 4, 2027 (Monday)
The first business day under the new rules, after the holiday and the weekend.
calendar
60 days after a complete application
On a lot with an existing house, the city must approve or deny it, or it's deemed approved.
[9]
April 2027
HUD says it will post revised Fair Market Rents from its rechecks.
[10]
What changes on January 1, 2027, and what doesn't?
What it is. Where today's law says one, AB 956 says "Two detached, new construction, accessory dwelling units that do not exceed four-foot side and rear yard setbacks for a lot with a proposed or existing single-family dwelling" [1]. The city may still cap each at "800 square feet of livable space" and apply the state's height limits. The unit made from existing space, inside the house or a garage, stays on the list [1].
News · September 29, 2026 · From January 1, 2027, for up to two ADUs on a lot, impact fees on an ADU count only the living space above 750 square feet. [2]
SB 1117 keeps the fee scaled to "the square footage of the primary dwelling unit," but charges it "only on the area in excess of 750 square feet of interior livable space" [2]. Connection fees and capacity charges aren't impact fees under the law, so this change doesn't touch them [2].
What it means for you. Neither law waits for a city vote. Both are regular statutes, which the state constitution starts on "January 1 next following a 90-day period from the date of enactment" [3]. HCD, the state housing department, hasn't caught up on paper: its ADU Handbook was last updated in March 2026, before either law was signed [11]. In the San Mateo example from our ADU payback guide, an 800-square-foot cottage behind an 1,800-square-foot house, transportation and child-care impact fees fall from about $3,100 to $5,300, depending on how the city classifies the cottage, to about $200 to $330 [12][13][2]. Same cottage, charged on 50 square feet instead of 800 for those two fees. Sewer capacity charges don't change, and SB 1117 doesn't say whether its rule reaches school fees [2][12].
Amiari Construction builds custom homes, ADUs and additions on the Peninsula.
Should you file your ADU permit before or after January 1?
What it is. Neither chaptered law has a transition rule or a later start date [1][2]. SB 1117 doesn't say whether the day you apply, the day the permit issues or the day the fee comes due decides which fee rule you get [2]. Under another state law, impact fees on a project of 10 or fewer units generally can't be collected before the first certificate of occupancy, temporary or not, or the final inspection where the city issues none [14]. The same law sets the amount at what would have been paid before the building permit was issued [14].
What it means for you. New Year's Day can even nudge a permit deadline. A city has 15 business days to say whether your application is complete, then 60 days from a complete application to approve or deny it on a lot with an existing house, or it's "deemed approved" [9]. By our count, day 60 for a complete application received on November 2 lands on January 1, 2027, a holiday. State law generally moves a deadline that falls on a holiday to the next day that isn't one, here Monday, January 4 [15].
One detached ADU of 750 square feet or less? The state path already allows it today [1], and it pays no city impact fee before or after, though a school district can still charge on one over 500 square feet [2][13].
Two detached ADUs, or one over 750 square feet? Ask the city, in writing, which rules and fees apply to an application filed in 2026 and decided in 2027, and which date it counts.
We can walk your lot with you.
What should you do before January 1, 2027?
What it is. The law sets the number. The fire hose, the sewer and the power decide whether that number fits your yard [16][17][18].
What it means for you. Spend the holidays on the checks that take longest:
Pace the hose path. Every first-floor outside wall must sit within 150 feet of the fire department's access road, usually the street, measured along the route around the building, unless the fire department allows more, for example with sprinklers [16]. Menlo Park Fire's longer, sprinklered allowance is written for driveways serving one or two homes, and a house with two cottages makes three [17]. Our two-ADU guide walks one example lot.
Find what's under the yard. Sewage usually needs at least a quarter inch of fall per foot, and a cottage that sits too low needs a pump [18]. San Mateo protects any oak, and Menlo Park any native oak, from 10 inches across [19][20]. See where an ADU can go.
Start with PG&E early. For jobs applied for since 2023 and finished by August 2025, PG&E's posted average for a new ADU service that didn't need a line extension was 303 days from application to power, counting the owner's and agencies' time as well as PG&E's own, which averaged 111 days [21]. The state's average target for the steps PG&E controls on a new service line is 182 days [22].
Call your lender. Fannie Mae allows up to three ADUs on a one-unit home only on loans with a UAD 3.6 appraisal, and counts rent from only one ADU [5]. That format is mandatory for new appraisal reports from November 2, 2026, though lenders with an exception can keep the old one through May 19, 2027 [6][7].
Take the free class. The San Mateo County ADU Resource Center's "Building Your ADU" webinar runs online on November 19, 5:30 to 6:30 pm, on contractors, bids, costs, phases and inspections. It's free; registration is required [8].
Amiari can walk the yard with you.
What does your city have to do, and by when?
What it is. From January 1, the two-ADU rule applies "Notwithstanding Sections 66314 to 66322," the sections behind a city's own ADU rules, and AB 956 sets no date for cities to rewrite their ordinances [1]. A city must also send each new ADU ordinance to HCD within 60 days of adopting it and answer HCD's findings within 30 days, or the ordinance is "null and void" and state standards apply [23].
What it means for you. Posted rules can lag the law. Menlo Park's chapter, in effect since July 10, 2026 [24], allows one new detached ADU on the state path [25]. HCD found it substantially compliant that June and added that "as State ADU Law is updated, the City's ordinance will need to continue to be updated as well" [26]. Our Menlo Park news and note on the void rule show how that plays out. Before you pay for drawings, ask the planning counter which rules it will apply, and keep the answer.
Amiari builds ADUs on the Peninsula and can look at your lot with you.
What happens after January 1, 2027?
What it is. A city "is not required to ministerially approve" a junior ADU, the small unit inside the house, "on the same lot where two detached, new construction, accessory dwelling units have been constructed" on the state path [1]. The fee break covers up to two ADUs on a lot. With more than two, impact fees on a unit over 750 square feet can be charged on the whole unit, still scaled to the house [2].
What it means for you. Order and count matter now. The junior ADU rule turns on units that "have been constructed," so if a junior ADU is in your plan, ask the city how it treats the order. A third ADU can cost the fee break on the others over 750 square feet, though any ADU of 750 square feet or less still pays no city impact fee, and a school district can still charge on one over 500 square feet [2][13]. As today, a new detached ADU can be required to have its own water or sewer connection, and that connection may carry a fee sized by its square feet or its drainage fixture units [2]. If rent is the plan, HUD says it will post revised Fair Market Rents from its rechecks in April 2027 [10].
Amiari Construction builds custom homes, ADUs and additions, and remodels kitchens and baths, on the Peninsula.
How we checked this: In October 2026, Amiari Construction read AB 956, SB 1117, Government Code §§6700, 66007, 66317 and 66326, Code of Civil Procedure §§12 and 12a and the state constitution in the legislature's own data download, HCD's ADU pages, handbook and Menlo Park letter, Menlo Park's news release, the fire, plumbing and tree rules, PG&E's posted timelines and the state's energization targets, Fannie Mae's and Freddie Mac's appraisal rules and their joint UAD timeline, San Mateo's fee schedule, HUD's rent notice, and the San Mateo County ADU Resource Center's event page.
Step by step
01Walk the yardPace the hose path from the street, and find the sewer line, the electric meter and any protected trees.
02Ask the city in writingAsk which rules and fees apply to an application filed before or after January 1, 2027, and which date counts.
03Size each unit on purposeFrom 2027, impact fees count only the living space above 750 square feet, for up to two ADUs on a lot.
04Start with PG&E earlyPG&E's posted average for a new ADU electric service with no line extension was 303 days from application to power.
05Plan the build orderOnce two detached ADUs are built on the state path, the city no longer has to approve a junior ADU on that lot, though it may.
From the job
Footings laid out beside a tree protection zone · Job photo · San Mateo
2027 ADU countdown: what to do before and after January 1amiari.com · 7 min read
Getting ready for January?Send us your address. We'll look at the yard, the sewer and the power, and tell you what to ask the city before anyone draws.
Have plans already, or need help getting started? We’ll help coordinate the right team and guide your project from the first ideas through construction. Prefer email? info@amiari.com
Share your projectAnswer a few quick questions about your project and goals.
We connectWe'll reach out within one business day to learn more and discuss your needs.
Plan and estimateWe'll provide preliminary insights and a clear path forward with next steps.
A
AmiariWe reply within one business day
San Carlos Whole Home Reconfiguration
Hi, we're Amiari. You were reading “2027 ADU countdown: what to do before and after January 1”. Let's talk about your home.