Hillsborough has no planning commission: staff approve smaller exterior projects, a five-member Architecture and Design Review Board hears new homes, teardowns, additions over 500 square feet and street-visible second stories, and its decisions can be appealed to the City Council.
Floor area is capped at 25 percent of the first acre of net lot area plus 15 percent beyond, and height follows an envelope that rises 22 feet at every setback line, then slopes in at 45 degrees to 32 feet.
Any tree of 18 inches or more in cumulative diameter is protected, and removal needs a permit, an arborist report, notice to adjacent owners and, in most cases, a 24-inch-box replacement.
News · April 13, 2026 · Hillsborough's City Council adopted Ordinance 800, a rewritten ADU chapter that adds a 15-business-day completeness check and council appeals of incompleteness findings and denials. [1][2][3]
Say you've loved your Hillsborough house for twenty years, and the kitchen finally has to go. Or you're ready to add a wing for the grandkids, or to tear down and build the house you've been sketching for years. Hillsborough has its own way of doing each of these, and knowing it up front can save months.
Here's the short version. Town staff handle permits and the smaller design reviews. A five-member Architecture and Design Review Board, the ADRB, hears the bigger exterior projects and appeals of staff decisions. The City Council hears appeals of the board's decisions. There's no planning commission [4][5]. Central County Fire Department reviews fire plans [6]. The town runs its own sewer and water, and PG&E brings the power [7][8][9].
Here's who reviews what, then how big you can build, the trees, teardowns, ADUs, fire and utilities.
Who reviews a Hillsborough remodel, addition, ADU or new home?
Project
Review path
Also check
Kitchen or bath remodel, interior only
Building permit; the town's like-for-like kitchen or bath line is $1,326 per permit with no wall changes (our fee note) [10]. The design review lists cover exterior and site work only [5]
The 1,500-square-foot sprinkler and sewer rules, the completion deadline and deposit (below)
Addition under 500 square feet
Staff-level review; staff can approve without public notice when they find "little or no negative visual effect" [5]
Floor area, lot coverage and the building envelope
Addition over 500 square feet
ADRB hearing [5]
Story poles if 22 feet or taller [11]
Second story
ADRB if visible from the street or over 500 square feet; staff if under 500 and not visible [5]
Story poles [11]
ADU or junior ADU
A ministerial ADU permit plus a building permit, with no hearing [2]
Sprinklers if the house has or needs them [2]
New home or teardown
A required planner meeting, then a Preliminary Review for every new house, then the ADRB hearing; new primary dwellings over 8,000 square feet also go to the council, unless the city planner, in consultation with the commissioner for the planning office, waives it after an ADRB vote with no dissent and no unresolved opposition [12][13][14][15]
Historic review for older houses, the demolition permit and the construction rules (below)
How does design review work?
What it is. In Hillsborough, "All exterior changes are subject to Design Review approval" [15]. The bigger ones go to the ADRB: new homes, teardowns, additions over 500 square feet and second stories you can see from the street [5].
What counts as a teardown? Removing "fifty percent or more of a dwelling's exterior walls, measured in linear feet." A wall stripped to the studs counts as removed, and the garage doesn't count at all. If a job not filed as a teardown crosses that line, the town stops the work until the ADRB approves a revised application [5][15].
Before a hearing, the town mails notice to owners within 500 feet at least 15 days ahead, and each board member visits the site [12]. Story poles go up for ADRB projects 22 feet or taller, new two-story houses and second-story additions [11].
How it helps or costs you. You get a planner's read early. The first meeting with a planner is required, and every new house gets a Preliminary Review, which isn't a public hearing, before the formal application [12][15]. A board decision can be appealed to the council within 15 days of the meeting, and council members can call it up in that same window [5]. An approval lapses if no building permit is issued within two years [5]. We found no overall timeline, only step deadlines, like allowing about 10 business days from first contact to schedule that first meeting [13].
What it means for you. Count the walls before you design. A remodel that quietly turns into a teardown starts over as a new house.
How big can you build in Hillsborough?
Start with the lot. Hillsborough's single-family zone, RD-1, allows one house per half acre, not counting ADUs [16]. Then three limits shape the house: how much floor area it can have, where it can sit and how tall it can be.
Floor area. The house can have floor area up to 25 percent of your net lot area for the first acre, plus 15 percent of anything beyond that [14]. On a lot with exactly one acre of net lot area, that's 10,890 square feet, by our arithmetic. Garages and accessory buildings count. So do rooms with ceilings of 7 feet or more (the town's July 2026 handout says 6 feet) and attics from 5 feet. Tall ceilings over 12 feet count at 150 percent after the first 300 square feet [14][15]. In a basement, areas with ceilings of 6 feet or more count at 33 percent if the walls rise less than 2 feet above natural grade, and in full at 2 feet or more [14].
Where it can sit. The house stays 25 feet from every street line and 20 feet from every other lot line [17]. There's a catch at the front. No part of the house can be closer than 50 feet to the middle of the street, up to 30 feet back from your front line [17]. Most streets in town are 40 or 50 feet wide, and on a 40-foot street the front setback becomes 30 feet [15]. On a 50-foot street, it stays at 25.
How tall it can be. Picture a tent over the lot. At each setback line, the limit rises 22 feet straight up from the existing ground. Where the land was graded before, the town uses the grade from five years before the permit application. Then it leans in at 45 degrees until it reaches 32 feet. That includes the pushed-back front line [18][17]. The house has to fit under the tent.
How much of the lot it covers. Buildings alone have a sliding cap: 4,495 square feet of footprint on a half acre of net lot area and 6,239 on a full acre, by our arithmetic. Buildings plus paving can't cover more than half the net lot area, or more than 40 percent of any setback area along a street [14].
News · August 10, 2026 · Hillsborough's City Council deferred adopting a cut to its 2,500-square-foot minimum house size, introduced July 13, "to a future meeting for further discussion." [19]
The 2,500-square-foot minimum is still in the code [14]. The pending proposal would lower it to 1,000 square feet for newly built homes [20].
What it means for you. Ask for your net lot area, and have the tent drawn on your own lot, before you fall for a floor plan.
Which trees are protected in Hillsborough?
Any tree of any species measuring 18 inches or more in cumulative diameter, 4 feet 6 inches above natural grade, is protected. So is any tree planted as a required replacement [21]. The bar dropped to 18 inches with an update the council adopted in March 2023 [22]. Around each one sits a protection zone: 5 feet past the dripline, the outer edge of the branches, or 15 feet from the trunk, whichever is bigger. It's fenced and signed during the work [21].
To take one down, you need the town's approval, a permit and an arborist's report. Within three business days of applying, you mail a notice to the neighbors next door. Each tree removed gets at least one 24-inch-box replacement within a year, or an in-lieu fee if the town finds the site can't hold it [21]. Cutting one without a permit can cost $150 per inch of trunk diameter, or the tree's appraised value if that's higher [21].
What it means for you. Measure the trunks first. In Hillsborough, a big oak or redwood can decide where the addition goes.
What else comes with a teardown or new home?
Historic review. A house over 50 years old may count as a potential historic resource under state environmental law. If you want to demolish one, the town's form points to a full historic evaluation [23]. Tearing down all or part of a historic resource takes a council-approved historic demolition permit. The code counts any historic resource under those state rules, plus five named estates [24].
Demolition and debris. You need a demolition permit [24], and a construction waste plan verified before any building or demolition permit is issued [25].
Construction hours. Weekdays run 8 a.m. to 5 p.m. On Saturdays, the town's Building Division page says 10 a.m. to 5 p.m., and the noise code keeps Saturday work quieter: 70 dBA at the property line, against 100 dBA measured 25 feet out on weekdays. No construction noise on Sundays or town holidays [26][27].
Running the site. From $500,000 in job value (over $200,000 for an owner-builder), a qualified superintendent must be on site, and the building official may call a preconstruction meeting. From $750,000, you need an approved construction management plan, covering parking, deliveries and dust, before the permit [28]. Moving 50 cubic yards of earth or more, counting cut and fill together, takes a grading permit. Hauling more than 1,500 cubic yards on or off the site also needs City Council approval and an environmental review. The town says that generally takes three to nine months [29][30].
Finishing on time. Deadlines run from 9 months for smaller jobs up to 30 months for jobs over $3 million. After a 30-day grace period, late work costs $200 a day, then $400 a day from day 61 and $1,000 a day from day 121 [31]. The fee schedule charges a completion deposit of 2 percent of valuation on permits over $50,000 [10]. The code sets the same 2 percent on any building permit, with a $500 minimum [31]. A new house's landscaping is due within six months of the certificate of occupancy [30].
Sprinklers and utilities. New homes get fire sprinklers [32], and utilities to and within the project go underground [30].
What do the 1,500-square-foot rules mean for a remodel?
Two town rules count how much you remodel, not just whether walls move.
Sprinklers. As the town publishes its code, they come in when two things are true. The existing house is over 2,000 square feet or more than two stories. And permitted additions and alterations pass 1,500 square feet, or 20 percent of a house over 7,500 square feet. A room counts as altered when half or more of its interior wall or ceiling covering comes off or goes on new. Work within two years of finishing earlier work adds up [32]. Before you plan around this trigger, confirm it with the building division or Central County Fire.
Sewer. Remodeling more than 1,500 square feet also brings an evaluation of the sewer lateral, and its repair or replacement if needed [33].
Most of the town's houses are old enough for state fixture rules too: 80 percent of Hillsborough's housing was built before 1980 [9]. Our bathroom permit guide explains what that brings.
What it means for you. If you're remodeling in phases, add up the rooms. Two modest projects inside two years can trigger sprinklers that neither would alone.
What do Hillsborough's ADU rules allow?
The rewritten chapter took effect 30 days after the council adopted it on April 13, 2026 [1][34]. Every ADU or junior ADU needs an ADU permit and a building permit, with no hearing. The town has 15 business days to say whether your application is complete, and 60 days to approve or deny a complete one [2].
State-standard units. A conversion ADU and a junior ADU, combinable with one new detached ADU of up to 800 square feet with 4-foot side and rear setbacks [2].
Taller cottages. A detached ADU can be 16 feet tall. It can go up to 22 feet when it's at least 20 feet from the side and rear lines and 25 feet from public rights-of-way [2].
Bigger units under local standards. Up to 850 square feet for a studio or one bedroom, and 1,000 for two or more, with design rules such as one story when detached and no roof decks [2].
Owner-occupancy. For a private owner, it applies only to a junior ADU that shares the house's bathroom. ADUs have none, and rentals must run at least 30 days [2].
The town issued building permits for 56 ADUs in 2025 [3]. Its ADU web page still describes the older rules, so go by the code [35][2]. For how the 2027 state changes add up, see how many ADUs you can build.
What about fire zones, sewer, water and power?
Fire. The State Fire Marshal's 2025 maps put parts of Hillsborough in High and Moderate zones, with no Very High, and the council adopted them in June 2025 [36][37][38]. Per the town's April 2026 staff report, the state's ignition-resistant construction rules reach fewer than 10 percent of parcels, those in High zones [34]. Class A roofing is required everywhere in town. That covers new roofs and any roofing used for an alteration, repair or replacement. When more than half a roof is replaced within a year, the whole roof has to be Class A [32]. Central County Fire Department serves the town, and its standard plan review takes 8 to 10 business days [39][6].
Sewer and water. The town's sewer is a "satellite system" that sends wastewater to Burlingame's and San Mateo's treatment plants [7]. The lateral must also be inspected when a home is sold [7]. All of Hillsborough's water comes from the San Francisco Public Utilities Commission [8].
Power and energy. PG&E delivers electricity [9]. The town dropped its 2022 energy reach code in 2024, and it took the 2025 state energy and electrical codes without local energy or wiring changes. So Hillsborough adds no 240-volt rule of its own, and the state codes apply as written [32]. Our 12-city permit guide compares kitchen rules across the Peninsula.
Our take: Hillsborough rewards patience and good neighbors. Most of the work here happens on paper before a shovel moves, so do it carefully.
Count the walls, then design. At half the exterior walls or more, a remodel is a teardown. If the job wasn't filed as one, the town stops the work until the ADRB approves a revised application [5][15]. We'd mark which walls stay on the very first sketch.
Draw the tent on the lot first. In our view, the 22-feet-then-45-degree height limit from every setback line can shape a second story as much as the floor area does [18]. We'd have it drawn before anyone falls for a roofline.
Treat the trees like neighbors. Any tree from 18 inches is protected, and the protection zone reaches 15 feet from the trunk at least [21]. We'd measure them before picking the addition's corner.
Plan the calendar backward. The completion deadline and its daily fines are real [31]. We'd set the schedule from the deadline, not from the start date.
Talk to the neighbors early. The town encourages outreach within 500 feet, and the application asks for each adjacent owner's signed form, or proof you mailed it [12][13]. A kitchen-table conversation now beats an appeal later.
Hillsborough homes are worth doing right, and the town's process is built for exactly that.
Amiari Construction builds custom homes, ADUs and additions, and remodels kitchens and baths, on the Peninsula.
How we checked this: In November 2026, Amiari Construction read Hillsborough's Title 15 building code (the town's December 2025 PDF), its zoning, design review, tree, demolition, construction and ADU chapters in a labelled third-party copy of the municipal code (text as of October 4, 2026, because the town's official code host blocked automated reading that day), the town's planning and building pages, handouts, fee schedules and standard conditions, council packets and minutes from 2025 and 2026, the housing element, and Central County Fire Department's pages. For the sewer lateral rule and the completion deadlines, we relied on the town's official code host as we read it in October 2026, and for the fire zones, also on the State Fire Marshal's 2025 acreage sheet as we read it in October.
Step by step
01Meet a planner firstBook the required pre-application meeting, and for a new house, plan on a Preliminary Review before the formal ADRB application.
02Count walls and square feetMark which exterior walls stay, and add up the remodeled area across two years, before the design is set.
03Measure the treesMeasure trunks 4 feet 6 inches above grade and mark each protection zone on the site plan.
04Talk to the neighborsReach out within 500 feet, and collect each adjacent owner's signed consultation form, or a certified-mail receipt if one doesn't answer, for the application.
Hillsborough remodel, addition or new custom home: the town's rulesamiari.com · 10 min read
Planning in Hillsborough?Send us your address and what you have in mind. We'll walk the lot with you, look at the walls, the envelope and the trees, and tell you what to ask the town before anyone draws.
Have plans already, or need help getting started? We’ll help coordinate the right team and guide your project from the first ideas through construction. Prefer email? info@amiari.com
Share your projectAnswer a few quick questions about your project and goals.
We connectWe'll reach out within one business day to learn more and discuss your needs.
Plan and estimateWe'll provide preliminary insights and a clear path forward with next steps.
A
AmiariWe reply within one business day
San Carlos Whole Home Reconfiguration
Hi, we're Amiari. You were reading “Hillsborough remodel, addition or new custom home: the town's rules”. Let's talk about your home.